Global Change

I got an event code error when updating baselines in P6.0

Can you please help us to resolve this issue. I have attached the print screen of the error we receive whenever we try to update baseline.

(See attached figure below: Error Message - Event Code D8E0794D )

Solution:

Why doesn't the [BL1 Start] column data match the [Start] column data when the Baseline is set to "Current Project"

When the Baseline is set to "Current Project", you might notice that activities with actual dates are not getting the right baseline.

Here is the solution:

1. Open Project Management Application, Click [Admin] menu, then select [Admin prreferences...].

Making Major Changes With Global Change

Global Change is a powerful feature of Primavera's Project Management software.  A Global Change is almost like a Microsoft Excel macro, but with some differences.  We'll walk you through how to program your own.